Kipi Calculator CURB & GUTTER CALCULATOR by Kipi Calculator

Curb & Gutter Calculator — Concrete Volume & Joints

    The run

    How long is the curb run, and how often do the contraction joints land?

    Station to station, corner to corner — the full length of curb and gutter you are pouring.

    Most city work spaces contraction joints about every 10 ft — match the pavement joints where the curb ties in.

    The profile

    The finished concrete section. A standard city profile is pre-filled — change any number to match your standard drawing.

    The curb stem stands on the pan. We count the pan once — its full width and thickness — plus the stem above it, so the concrete under the curb is never counted twice.

    Your concrete

    Waste allowance Starts at 0% — tap to add a cushion for cuts & breakage.

    Concrete needed

    – yd³

    Cubic feet
    –
    Per 100 ft
    –
    Cross-section
    –
    Contraction joints
    –

      💡 Pro field tips

        🧰 Tools you'll need

        Tap to check off as you load up.

        Project cost estimate (optional — concrete priced on the exact volume, before waste and round-up)

        File this estimate under a job name or PO to track what to order. Leave blank to file under "General".

        Assumptions & limits: Profile dimensions are the finished concrete section — a standard city profile is a 24 in gutter pan, 6 in thick, with a 6 in curb standing 6 in above the pan, but every city publishes its own standard drawings and yours governs — check them before you order. Volume is concrete only: the compacted aggregate base under the pan is not included — figure it as its own layer if your section calls for one. Typical curb and gutter spec is 4,000 psi concrete, air-entrained in freeze–thaw country. Waste and order figures are planning numbers — confirm with your batch plant and local standard before you pour.

        How the math works

        Curb and gutter is a prism: the same cross-section, extruded down the street. So the whole job is two rectangles and one multiplication.

        The cross-section: two rectangles, counted once

        Gutter pan = Pan width × Pan thickness — 24 in × 6 in = 144 in²

        Curb stem = Curb width × Reveal — 6 in × 6 in = 36 in²

        Cross-section = Pan + Stem — 144 + 36 = 180 in² = 1.25 ft²

        The stem stands on the pan, and the pan rectangle already includes the concrete under the stem — so the stem only counts the part above the pan (the reveal). Adding a full-height curb block on top of a full-width pan would count that corner of concrete twice.

        Volume: area × length

        Volume (ft³) = Cross-section (ft²) × Run length (ft) — 1.25 × 100 = 125 ft³

        Cubic yards = ft³ ÷ 27 — 125 ÷ 27 = 4.63 yd³

        Yards per 100 ft: the bidding shortcut

        Once you know the per-100-ft figure for a profile — 4.63 yd³ per 100 ft for the standard section above — pricing a long run is one multiplication: a 650 ft street at the same profile is about 6.5 × 4.63 ≈ 30.1 yd³ before waste.

        Contraction joints

        Concrete shrinks as it cures, so curb gets a tooled or saw-cut joint about every 10 ft to tell it where to crack. The count here is the simple planning version: joints ≈ run length ÷ spacing, rounded — end joints land at corners, driveways, and tie-ins, which you place by eye on the day.

        Worked example: 100 ft at the standard profile

        • Section: (24 × 6) + (6 × 6) = 180 in² = 1.25 ft²
        • Volume: 1.25 × 100 = 125 ft³
        • Yards: 125 ÷ 27 = 4.63 yd³ — with 10% waste, order about 5.25 yd³
        • Joints at 10 ft spacing: about 10 joints

        Straight curb, honest yardage.

        Most Asked Questions

        How much concrete is in 100 ft of curb and gutter?

        4.63 cubic yards at the standard city profile. A 24-in gutter pan 6 in thick, plus a 6-in curb with a 6-in reveal, makes a 1.25 ft² cross-section — 125 ft³ over 100 ft. Add 10% waste and the order comes to 5.25 yd³.

        What is a standard curb and gutter profile?

        A 24-inch gutter pan, 6 inches thick, with a 6-inch curb standing 6 inches above the pan. Some cities spec a 30 or 36 in pan, a rolled curb, or a mountable profile instead. Always check the local standard drawings — they govern the profile, the joints, and the mix.

        Does this include the gravel base under the gutter?

        No — this figures the concrete section only. Most curb sits on a compacted aggregate base. If your section calls for one, figure that base as its own layer, with its width and thickness from the standard drawing.

        How far apart should contraction joints be?

        About every 10 ft is the usual city standard. This count is run length ÷ spacing, rounded — 100 ft at 10 ft spacing is 10 joints. Joints should line up with the pavement joints behind the curb where you can, and you'll still add them at corners, radius points, and driveway tie-ins on the day.

        What strength concrete is used for curb and gutter?

        4,000 psi is the typical municipal spec. Air-entrained where the curb sees freeze–thaw cycles and de-icing salt. Your city's standard drawings and the project specs govern — check them before you order.

        How do I price a long run of curb?

        Multiply the per-100-ft figure: 4.63 yd³ per 100 ft at the standard profile. A 650 ft street is 6.5 × 4.63 ≈ 30.1 yd³ before waste. Change the profile and the per-100 figure changes with it — that's why the dimensions are editable.

        Next calculation

        One job usually leads to the next number. Common next steps from here:

        Embed this calculator on your site

        Run a DIY, contractor, or supplier site? Put this curb & gutter calculator — concrete volume & joints right on your page, free. Copy the code and paste it where you want it — your visitors get the numbers without leaving your site.

        Free to use. The small “Powered by Kipi Calculator” line at the bottom of the calculator stays on — that’s all we ask.