Kipi Calculator REBAR CALCULATOR by Kipi Calculator

Rebar Calculator

    How are you figuring it?

    Two ways in — lay out a slab grid, or work from a footage total you already have.

    Your slab & steel

    Rebar is sold in 20-ft sticks — that's what the count is figured on.

    Bars stop 3 in short of each edge for concrete cover — that's already in the math below.

    Bar spacing
    Bar size — standard weight per foot shown

    Waste allowance — extra for cutting waste & lap splices

    Your rebar order

    Order this many

    – sticks

    How this is figured: in a slab grid each bar stops 3 in short of the edges (concrete cover), and sticks are 20 ft, the standard stock length. Total weight is the weight of the steel you're buying — the full sticks — at the standard bar weights, not just the footage that ends up in the slab.

    Linear feet (exact)
    –
    No waste added
    –
    Total weight
    –of the steel you're buying
    Weight in tons
    –

      💡 Pro field tips

        🧰 Tools you'll need

        Tap to check off as you load up.

        Est. project cost (optional)

        File this estimate under a job name or PO to track what to order. Leave blank to file under "General".

        How the math works

        Rebar isn't sold by the foot off a roll — it's sold by the 20-ft stick. So a rebar estimate runs in that order: figure the steel the job actually needs in linear feet, add a waste allowance for cuts and laps, then convert to sticks and weight. Weight matters too — it decides whether the delivery rides on your truck or theirs.

        The grid: bars both ways, held 3 inches off the edges

        In a slab, bars run in both directions at your spacing. Steel needs concrete cover to protect it, so each bar stops 3 inches short of the slab edges — a bar's run is the slab dimension minus 6 inches total. The count in each direction is the run divided by the spacing, rounded down, plus one for the bar at the start:

        Bars per direction = (Dimension − 6″) ÷ Spacing, rounded down, + 1

        Total linear feet = (Bars one way × their length) + (Bars the other way × their length)

        Sticks: add waste first, then divide by 20

        Cutting a 20-ft stick down to a 19.5-ft bar leaves a drop, and every lap splice eats footage. The calculator adds your waste percentage to the linear feet before the stick count, so the extra steel is really there:

        Sticks to buy = (Linear feet × (1 + your waste %)) ÷ 20, rounded up — the waste chips start at 0%, so the exact count is what you get unless you tap a chip to add more

        Weight: standard pounds per foot

        The bar number is the bar's diameter in eighths of an inch — a #4 bar is 4/8, or ½ inch across. Each size has a standard published weight per foot, and those are the weights used here:

        • #3 — ⅜″ diameter · 0.376 lb/ft
        • #4 — ½″ diameter · 0.668 lb/ft
        • #5 — ⅝″ diameter · 1.043 lb/ft
        • #6 — ¾″ diameter · 1.502 lb/ft
        • #7 — ⅞″ diameter · 2.044 lb/ft
        • #8 — 1″ diameter · 2.670 lb/ft

        Total weight = Sticks × 20 ft × Weight per foot

        That's the weight of the steel you're buying — full sticks, before cutting — which is the number that matters for hauling and delivery.

        How this compares to the rebar in the concrete calculator

        The concrete calculator has a quick rebar estimate built in: #4 bars on a fixed 18″ grid, run the full length of the slab. This standalone tool is the detailed version — you pick the bar size and the spacing (12″, 16″, 18″ or 24″), and bars are held 3″ off the edges the way they're actually placed. Expect the two to land close but not identical on the same slab; use this one when steel is the order you're placing.

        Worked example: 20 × 20 ft slab, #4 bars at 12″ on center

        • Bar run: 20 ft − 6 in = 19.5 ft each way
        • Bars per direction: 19.5 ÷ 1 ft = 19.5 → rounded down + 1 = 20 bars
        • Total steel: 20 bars × 19.5 ft, both ways = 780 lin ft
        • At 0% waste (the chips start at 0%): sticks: 780 ÷ 20 = 39 sticks
        • Weight at 0%: 39 sticks × 20 ft × 0.668 lb/ft = about 521 lb (0.26 tons)
        • If you tap +10% for cuts and laps: 780 × 1.10 = 858 lin ft → 858 ÷ 20 = 42.9 → 43 sticks, about 574 lb (0.29 tons)

        Thirty-nine sticks of #4 exact — forty-three if you tap +10% — under 600 pounds either way: one pickup load, figured in under a minute.

        Worked example

        You're tying steel for a 20 × 20 ft garage slab, #4 bars on a 12-inch grid. Using this calculator's own math:

        • Bars: 20 each way at 19.5 ft = 780 lin ft of steel in the mat
        • At 0% (the waste chips start at 0%): order 39 sticks of 20-ft #4 — weight ≈521 lb
        • If you tap +10% for cuts and laps: 858 lin ft → 43 sticks, ≈574 lb — the yard can forklift it onto your truck in one bundle

        One trip to the steel yard with real numbers — no guessing, and no second trip for two sticks on pour morning.

        On a real job

        • Chairs are not optional. Steel belongs in the middle of the slab, not on the dirt — chairs or dobies every few feet hold the mat at height while you walk and pour.
        • Lap splices: 40 bar diameters is the common rule. That's about 20″ for #4 and 30″ for #6. Stagger the laps so they don't all land in one line, and check your plans or local code.
        • Cut long bars first. Work the cut list from the longest pieces down — offcuts from long bars become your short bars instead of scrap.
        • Surface rust is fine; flaking scale is not. Light rust actually helps the bond. Loose, flaking rust should be wire-brushed off before the pour.
        • Order tie wire and chairs with the steel. A spool of tie wire and a bag of chairs on the same ticket saves a second trip on pour day.

        Most Asked Questions

        How many sticks of rebar do I need for a 20 × 20 ft slab?

        39 sticks of #4 at 12″ spacing — 780 lin ft of steel, about 521 lb. Bars stop 3″ short of every edge, so each one runs 19.5 ft: 20 bars each way × 19.5 ft = 780 lin ft, and 780 ÷ 20-ft sticks rounds up to 39.

        Why do the bars stop 3 inches short of the edges?

        Steel needs concrete cover, or it rusts and loses its grip. Every bar stops 3″ from the form, so each run is the slab size minus 6″ — a 20-ft slab takes 19.5-ft bars. That's already in the count; you don't subtract anything yourself.

        How much does #4 rebar weigh?

        0.668 lb per foot — about 13.4 lb for a full 20-ft stick. The weight in your results is the steel you're actually buying — full sticks, before cutting. The 20 × 20 slab above totals 521 lb at the exact count, about 0.26 tons.

        Does the waste percentage cover lap splices?

        Yes — that's what it's for. The grid count is exact bar length. The waste chips (they start at 0%) add your allowance for cuts and lap splices before the stick count: at 10%, the 20 × 20 slab goes from 39 sticks to 43 — 858 lin ft, about 574 lb.

        How much does spacing change the count?

        A lot — wider spacing drops the steel fast. Same 20 × 20 slab in #4: at 12″ spacing it takes 780 lin ft (39 sticks); open it up to 18″ and it's 546 lin ft (28 sticks). Use the spacing your plans or code call for — the count follows it.

        I already know my linear feet. Can I skip the slab grid?

        Yes — use the Linear feet option. Enter the total feet of bar and the bar size, and you get sticks and weight straight away: 500 lin ft of #5 comes out to 25 sticks, about 522 lb.

        Next calculation

        One job usually leads to the next number. Common next steps from here:

        Working on a whole slab? Project Mode chains concrete, gravel base, rebar and forms into one order list.

        Embed this calculator on your site

        Run a DIY, contractor, or supplier site? Put this rebar calculator right on your page, free. Copy the code and paste it where you want it — your visitors get the numbers without leaving your site.

        Free to use. The small “Powered by Kipi Calculator” line at the bottom of the calculator stays on — that’s all we ask.

        Popular lookups

        10×10 slab · 12×12 slab · 20×20 slab · 20×30 slab · 24×24 slab · All charts