Sewer Line Grade Calculator
The run
Where the line starts, and how far it runs — to the main, the manhole, or the next cleanout.
The inside bottom of the pipe at the start — off the plans or your last shot.
End to end of the run you are grading — building to main, or manhole to manhole.
Smaller pipe needs more slope to stay self-cleaning — the results check your grade against the usual minimum for the size you pick.
The fall
How much drop does this run get? Either way works.
Sewer grades are usually called in inches per foot: ¼ in/ft ≈ 2.08%, ⅛ in/ft ≈ 1.04%.
Bury depths
Optional — add the rim (surface) elevation at each end and we will figure the bury depth, rim down to invert. Skip it if you just need the grades.
Rim = finished ground, manhole lid, or cleanout top at that end — from the plans or your shot. Bury depth runs down to the invert; the dirt cover over the pipe itself is less, by about the pipe's outside diameter.
Your grades
End invert elevation
– ft
- Total fall
- –
- Slope
- –
- Slope per foot
- –
- Fall per 10 ft
- –
- Pipe size
- –
- Bury depth — start end (rim to invert)
- –
- Bury depth — end (rim to invert)
- –
📏 Grade table
| Distance from start | Invert elevation | Drop from start |
|---|
💡 Pro field tips
🧰 Tools you'll need
Tap to check off as you load up.
File this run under a job name or PO to keep the grades with the job. Leave blank to file under "General".
Copied to clipboard ✓
How the math works
A sewer line is one straight downhill run between two inverts — the building and the main, or manhole to manhole. The elevations work in feet and hundredths (0.01 ft is about 1/8 inch, and in the trench the drop gets called in tenths off the rod), but sewer grades themselves are usually specified one more way: inches per foot. This calculator speaks all three.
Slope: percent and inches per foot
Percent slope is the fall spread over the run. Inches per foot is the same slope in the units on most sewer plans and code tables:
Slope % = (Start invert − End invert) ÷ Run length × 100
Inches per foot = Slope % × 12 ÷ 100 — so 2.08% is ¼ in per foot, and 1.04% is ⅛ in per foot
Total fall (ft) = Run length × Slope % ÷ 100
The end invert
Subtract the fall from where you started:
End invert = Start invert − Total fall
Stations: the grade at any point
Once you have the slope, the invert at any distance down the run is the start minus that distance's share of the fall:
Invert at distance d = Start invert − (d × Slope % ÷ 100)
The grade table in the results does this every 10 ft (every 25 ft on long runs) so you can set the laser, shoot each station, and catch a belly or a high spot before the bedding goes in — a belly in a sewer is a clog that hasn't happened yet.
Minimum slope: smaller pipe needs more fall
A sewer has to move solids, not just water, so the smaller the pipe, the steeper the usual minimum. The planning values used here:
- 4 in building sewer: 2.08% (¼ in per foot)
- 6 in: 1.04% (⅛ in per foot)
- 8 in: 0.40%
- 10 in: 0.28%
- 12 in: 0.22%
- 15 in: 0.15%
Local code and the project plans govern — they can and do require more.
Bury depth: rim minus invert
How deep the line lies at either end:
Bury depth = Rim (surface) elevation − Invert elevation
The cover over the pipe — the dirt between the surface and the top of the pipe — is the bury depth minus the pipe's outside diameter. Crews use bury depth to call trench depth and shoring; inspectors and frost depth care about cover.
Worked example: 100 ft building sewer, start invert 100.00, 4 in pipe at ¼ in per foot
- Slope: ¼ in per foot = 2.08%
- Total fall: 100 × 2.08 ÷ 100 = 2.08 ft (24.96 in)
- End invert: 100.00 − 2.08 = 97.92
- Fall per 10 ft: 0.21 ft (2.5 in · 2.1 tenths)
One line, falling a quarter inch with every foot, from the building to the main.
Worked example
An 80-ft building sewer in 6-inch pipe, leaving the building at invert 100.00, run at ⅛ inch per foot (1.04%) — the usual minimum for 6-inch:
- Total fall: 80 × 1.04 ÷ 100 = 0.83 ft — right at 10 inches of drop, end to end
- End invert at the main: 100.00 − 0.83 = 99.17
- Drop every 10 ft: 0.10 ft (1¼ inches — about one tenth on the rod)
- Slope check: 6-inch minimum is 1.04%. This run sits exactly on it — there is no room to flatten anywhere along the line.
Ten inches of fall over eighty feet. That's the whole job: protect those ten inches.
On a real job
- Local code governs — check it before you dig. Some jurisdictions require ¼ inch per foot on a 6-inch building sewer instead of ⅛. The plans and the inspector outrank any calculator, including this one.
- A belly is a clog that hasn't happened yet. Bed the pipe on shaped gravel, keep the fall continuous, and shoot every station. Solids settle anywhere the line sags, and they do not forgive.
- Plan the cleanouts while the trench is open. Code typically wants one where the line leaves the building and at intervals on long runs. A cleanout costs little in an open trench and a fortune through finished concrete.
- Call 811 before the bucket touches dirt. Locates are free; a hit gas line or fiber cut is not. Wait for the marks and dig careful inside the tolerance zone.
- Test before you backfill where required. Many inspectors want a water or air test on the line first. Backfilling an untested line that fails means digging your work up twice.
Most Asked Questions
What is the minimum slope for a sewer line?
Smaller pipe needs more fall: 1/4 in per foot (2.08%) for 4-inch, 1/8 in per foot (1.04%) for 6-inch. The bigger sizes run flatter — 8 in: 0.40%, 10 in: 0.28%, 12 in: 0.22%, 15 in: 0.15%. Those are the usual planning minimums this calculator flags; local code and your project plans govern and can require more.
Can I use this calculator for a septic line?
Yes — a septic line is graded exactly like a building sewer. Enter the start invert, run length, and pipe size and you get the end invert, total fall, and a station-by-station grade table, with the same minimum-slope checks. Your local health department's permit rules govern the final design.
Why does a sewer line need slope at all?
Sewer flows by gravity — the water has to move about 2 feet per second to carry the solids with it. Too flat and the flow slows, solids settle out, and the line starts to clog. Too steep isn't free either: the water can outrun the solids, and the pipe may need anchors or drop structures.
What is an invert — and what is bury depth?
The invert is the inside bottom of the pipe — every grade is measured to it, never to the top (crown). Bury depth is how far the pipe sits below the surface: rim (ground, manhole lid, or cleanout top) minus the invert. The cover over the pipe is the bury depth minus the pipe's outside diameter.
What is the difference between a building sewer and a sewer main?
The building sewer is the smaller line — usually 4 or 6 in — from the building out to the street. The main is the larger line (8 in and up) running down the street that laterals tie into, with manholes where it changes direction, size, or slope. More flow in a bigger pipe means the main can run at much flatter grades.
How much fall is 1/4 inch per foot over 40 feet?
10 inches — 40 ft × 1/4 in = 10 in, which is 0.83 ft. The conversion both ways: slope % × 12 ÷ 100 gives inches per foot, and inches per foot × 100 ÷ 12 gives percent. So 1/4 in per foot is 2.08%.
Popular lookups
All charts · 4″ over 50 ft · 4″ over 100 ft · 6″ over 100 ft