Storm Drain Grade Calculator
The run
Where the pipe starts, and how far it runs to the next box.
The inside bottom of the pipe at the first box — off the plans or your last shot.
Box to box, center to center.
The fall
How much drop does this run get? Either way works.
1% is a common plan slope. 0.5% is the usual minimum.
Box depths
Optional — add rim elevations and we will figure how deep each box runs. Skip it if you just need the grades.
Rim = top of the grate, from the plans or finished grade. Leave either one blank to skip it.
Your grades
End invert elevation
– ft
- Total fall
- –
- Slope
- –
- Fall per 10 ft
- –
- Pipe size
- –
- Start box depth (rim to invert)
- –
- End box depth (rim to invert)
- –
📏 Grade table
| Distance from start | Invert elevation | Drop from start |
|---|
💡 Pro field tips
🧰 Tools you'll need
Tap to check off as you load up.
File this run under a job name or PO to keep the grades with the job. Leave blank to file under "General".
Copied to clipboard ✓
How the math works
Setting storm pipe is setting one straight downhill line between two box inverts. Everything works in feet and hundredths — 0.01 ft is about 1/8 inch, so an elevation like 98.80 is read "ninety-eight eighty." In the trench, grade gets called in tenths off the rod — so every drop in the results is shown in tenths too. Three pieces of math run the whole job: slope, the end invert, and the stations in between.
Slope: fall per hundred feet
Slope percent is just the fall spread over the run. If you know both inverts, the slope falls out of them; if you know the slope, the fall does:
Slope % = (Start invert − End invert) ÷ Run length × 100
Total fall (ft) = Run length × Slope % ÷ 100
So 1% over 120 ft is 120 × 1 ÷ 100 = 1.20 ft of fall — and every 10 ft of that run drops 0.10 ft, about 1-3/16 inches. That per-10-ft number is the one you actually dig to.
The end invert
Subtract the fall from where you started:
End invert = Start invert − Total fall
Stations: the grade at any point
Once you have the slope, the invert at any distance down the run is the start minus that distance's share of the fall:
Invert at distance d = Start invert − (d × Slope % ÷ 100)
The grade table in the results does this every 10 ft (every 25 ft on long runs) so you can set the laser, shoot each station, and catch a belly or a high spot before the bedding goes in — not after the backfill.
Box depth: rim minus invert
A box is as deep as the distance from its grate to its invert:
Box depth = Rim elevation − Invert elevation
That number tells the crew how many riser sections to stack and how deep the excavation has to go at each structure.
Worked example: 120 ft run, start invert 100.00, 1% slope
- Total fall: 120 × 1 ÷ 100 = 1.20 ft (14.4 in)
- End invert: 100.00 − 1.20 = 98.80
- Halfway (60 ft): 100.00 − 0.60 = 99.40
- Box depths with rims at 104.50 and 103.00: 104.50 − 100.00 = 4.50 ft and 103.00 − 98.80 = 4.20 ft
One line, falling 0.10 ft every 10 ft, from box to box.
Worked example
A 200-ft run of storm pipe between two boxes. The plans call for a start invert of 96.50 at 0.5% slope, with rims at 100.00 (start box) and 99.20 (end box). Here's the run, figured:
- Total fall: 200 × 0.5 ÷ 100 = 1.00 ft
- End invert: 96.50 − 1.00 = 95.50
- Drop every 10 ft: 0.05 ft — that's 0.6 inch, or half a tenth on the rod, station after station
- Halfway (100 ft): 96.50 − 0.50 = 96.00
- Box depths: 100.00 − 96.50 = 3.50 ft at the start box; 99.20 − 95.50 = 3.70 ft at the end box
Half a tenth sounds like nothing — but hold it steady for 200 feet and the line drains like it's supposed to.
On a real job
- Convert before you dig. Plans read in hundredths; the trench calls grade in tenths off the rod. Do the conversion at the truck, not standing in the ditch — 0.05 ft of fall per station is half a tenth, every time.
- Check the laser against the benchmark at every setup. A bumped tripod or a moved hub ruins a whole run quietly. Re-shoot the benchmark before the first pipe and after any break.
- Bed the pipe, don't just lay it. Lumpy trench bottom makes bellies. A shaped bed of sand or fine gravel under the barrel, with bell holes dug at each joint so the pipe bears on its barrel — not its bells — keeps the grade you shot.
- Verify the end invert before backfill. Shoot the last pipe against the downstream box while the trench is still open. Grade is never cheaper to fix than right then.
- Watch the minimums. Half a percent is the usual floor for storm pipe; flatter than that and grit settles, the line silts up, and the "drainage problem" becomes next year's excavation.
Most Asked Questions
What's the minimum slope for storm pipe?
0.5% is the usual floor, and 1% or more keeps storm pipe self-cleaning. Some pipe sizes and jurisdictions allow flatter grades, but flatter pipe silts up faster. Always check the run against your project plans and local spec before you dig.
What is an invert, exactly?
The inside bottom of the pipe. Invert elevations are the numbers the whole run is set by — start invert at the first box, end invert where the pipe lands in the next box, and the end always has to be lower than the start.
How much fall is 1% over my run?
1% means 1 foot of fall per 100 feet — 0.10 ft every 10 feet, about 1-3/16 inches. That per-10-ft number is the one you actually dig to, station by station.
Why do the plans say 98.80 but the crew calls out tenths?
Plans are written in hundredths of a foot; grade in the trench gets called in tenths off the rod. One hundredth (0.01 ft) is about 1/8 inch. An elevation of 98.80 is read "ninety-eight eighty" — and this calculator shows every drop in tenths too, the way it's called in the field.
Can this calculator replace my plans?
No — it does the math on the numbers you give it. Enter inverts from your project plans, tied to the site benchmark. The calculator figures slope, end invert, box depths and the station-by-station grade table; the plans and local code are still the authority.
What else do I get besides the end elevation?
The full grade table. Distance from start, invert elevation and drop at every station, plus start and end box depths if you add the rim elevations — everything the crew needs to set the run without re-doing math at the trench.
Where do storm drain boxes go?
Where the water collects: low points, grade breaks, and anywhere the pipe changes direction or size. Plans set the layout and spacing — about 300 ft apart is a typical maximum on roadways, and low points always get one. This calculator figures the grade for a run between two boxes; it doesn't lay out the system.
Popular lookups
All charts · 8″ over 100 ft · 12″ over 100 ft · 15″ over 200 ft